This video will guide you at the installation and programmation but does not dispense the consult of the product’s manual
01 – INSTALLATION – AUTOMATISM
——————————————————————————————————————————————
00:40 – Pre installation
01:20 – KIT Bravo 500 composition
02:37 – Motor’s application
02:42 – Create cement foundation
04:18 – Existing foundation
05:28 – Fixing the motor to the cement foundation
06:15 – NYLON rack
07:10 – METAL rack
09:06 – Limit-switches plates
10:13 – Tuning the clutch
——————————————————————————————————————————————
01 – INSTALLATION – COMPONENTS
——————————————————————————————————————————————
13:37 – MF1 Photocells
16:53 – MP101 Lightbulb
18:57 – SCMV Key Selector
20:32 – MA4 Antenna
21:50 – Passing component cables – Controlboard connections
——————————————————————————————————————————————
03 – MAINTENANCE
——————————————————————————————————————————————
24:09 – Check distances and grips
26:04 – Check friction between the rack and pinion
27:18 – Lubricate components